The dismantling of the historic Elphinstone Road Over Bridge (ROB), a century-old structure built in 1913 during the British era, began on Friday as part of a broader infrastructure overhaul linked to the ambitious Sewri -Worli Elevated Connector project of MMRDA. The estimated cost of this Double Decker Bridge is Rs. 168 crore.
The completion period of the Railway portion is around 1 year after dismantling of existing ROB. According to sources, authorities are targeting to complete the dismantling and reconstruction work in two years.
Originally slated for completion within 20 days, the schedule has now been extended until July 10, 2025, due to constraints around railway traffic blocks. The dismantling of the approach roads — excluding the section directly above railway tracks — is expected to conclude by May 30, 2025.
This phase alone involves the removal of around 16,316 cubic meters of solid structures using heavy equipment, including two Poclain.
You may also like
New York stabbing: Commuter killed in subway system after row with man about shoes
In this scheme, the poor get a pension, only this much money has to be deposited in a month.
Florida's St Pete-Clearwater International Airport receives bomb threat, forces evacuation of Allegiant flight
NMCG clears 2025 action plan to keep river stretches along 145 cities healthy
"We have to go out, express ourselves": KKR all-rounder Moeen Ali ahead of clash against PBKS